ManTech EDC
Project Location: Parkway Drive, Hanover, Maryland
Total Contract Value: $716,000
Project Duration: 6-weeks
Reference: Darlene Frantz, Director of Real Estate and Facilities
This project was a 1,500 SF data center with three 45-ton up-flow CRAC units, two 40KVA UPS units, and clean agent Inergen fire suppression system with new annunciator panel. Coordinated and installed new innerduct/communication cabling through ManTech and adjacent tenants classified spaces. Project also included a coordinated building wide electrical shut down for installation of new 800A service.